Project Summary
InterPlan was hired to assist, as a sub-consultant, for the Environmental Impact Statement of SR-108 (2000 West) in Davis and Weber Counties. InterPlan's role consisted of extensive travel demand and traffic simulation modeling to assist in the overall project purpose and need and to identify and screen alternatives. Key staff from InterPlan were authors of several sections of the EIS document.
Client
Randy Jefferies, P.E.
UDOT Region 1 Project Manager
(801) 612-4043
Key Staff
Vern Keeslar, AICP
Matt Riffkin, P.E.
Rob Eldredge, AICP
Thomas McMurtry
Project Budget: $122,000
Timeframe: June 2006 - September 2007